I have a simulation that runs from mid-1999 to mid-2000. Below are some excerpts from the log file's time-step output.
Shortly after 2000-02-28 12:30, the date string switches from 2000-02-28 (which is correct) to 1999-03-**:
Code: Select all
282840 2000-02-28 12:30:-0.00 7.232136E-03 9.595376E+03 9.595384E+03 6.127136E+13
(268,100,11) 3.108790E-02 1.518986E-02 3.171568E-01 2.214117E+00
282841 2000-02-28 12:31:15.00 7.248462E-03 9.595342E+03 9.595349E+03 6.127158E+13
(268,100,11) 3.125993E-02 1.464380E-02 3.242527E-01 2.211739E+00
282842 1999-03-** 12:32:30.00 7.264872E-03 9.595307E+03 9.595314E+03 6.127180E+13
(268,100,11) 3.140089E-02 1.412618E-02 3.304424E-01 2.209156E+00
282843 1999-03-** 12:33:45.00 7.281359E-03 9.595272E+03 9.595279E+03 6.127202E+13
(268,100,11) 3.151144E-02 1.363791E-02 3.357258E-01 2.206374E+00
Code: Select all
283390 1999-03-** 23:57:30.00 6.609699E-03 9.595895E+03 9.595902E+03 6.126093E+13
(225,230,13) 1.395998E-03 3.059932E-03 3.169761E-01 1.516077E+00
283391 1999-03-** 23:58:45.00 6.614548E-03 9.595888E+03 9.595895E+03 6.126107E+13
(225,230,13) 1.458596E-03 3.071249E-03 3.169640E-01 1.530639E+00
283392 1999-03-00 00:00:-0.00 6.619608E-03 9.595881E+03 9.595888E+03 6.126121E+13
(225,230,13) 1.520579E-03 3.081869E-03 3.169531E-01 1.544468E+00
283393 1999-03-00 00:01:15.00 6.624877E-03 9.595874E+03 9.595880E+03 6.126135E+13
(225,230,13) 1.582087E-03 3.091852E-03 3.169484E-01 1.557555E+00
Code: Select all
284542 1999-03-00 23:57:30.00 6.650543E-03 9.595797E+03 9.595804E+03 6.125572E+13
(225,230,13) 3.434859E-03 3.093516E-03 2.980265E-01 1.128973E+00
284543 1999-03-00 23:58:45.00 6.647596E-03 9.595823E+03 9.595830E+03 6.125571E+13
(225,230,13) 3.363811E-03 3.093947E-03 2.981194E-01 1.129141E+00
284544 2000-03-01 00:00:-0.00 6.644884E-03 9.595848E+03 9.595855E+03 6.125571E+13
(225,230,13) 3.295401E-03 3.093909E-03 2.982116E-01 1.129228E+00
284545 2000-03-01 00:01:15.00 6.642410E-03 9.595873E+03 9.595879E+03 6.125570E+13
(225,230,13) 3.229865E-03 3.093444E-03 2.983071E-01 1.129230E+00
I haven't run the model through any other February-March transitions